← David Randolph Case 01 / 05 · Public version

On My Way

Too many of National Grid's field jobs still ran on paper and phone calls. I led the rebuild of the app that lets a crew take a job, do it and close it without driving back to the barn.

45→83%
Share of jobs crews completed in the app

Instead of on paper or by calling in, before and after the rebuild. The project received National Grid's Chairman's Award.

Role
Lead for strategy and product design. Business and data analyst. Interim PM for 3 months.
Team
2 designers, 1 researcher, 2 PMs, 16 engineers, 2 business strategists, 2 business owners, 2 change managers
Timeline
Nov 2023 – Jun 2024 · National Grid
Methods
Field studies, SME and user interviews, 8 moderated usability sessions, mid-sprint reviews
ProblemCrews drove back to the barn for paperwork and called in for their next job. Every paper hand-off was a place work could stall.
My roleI led strategy and product design for the rebuild and replatform of the service-job apps, and for three new feature areas.
ResultJobs completed in the app rose from 45% to 83%. In usability testing, task success went from 68% to 95% and task time fell 32%.

The problem

Every hand-off was a place work could stall.

On My Way (OMW) is National Grid's mobile and web app for electric field work. About 1,500 crew members use it on mobile and 250 supervisors use it on the web. One service job passes through many hands: a crew takes it, logs time, and sends paperwork to a supervisor, and the approved paperwork moves on to the team that closes the work order.

Design question

How might we take a job from request to closed without paper changing hands?

My part

What was mine, and what wasn't.

OMW launched in 2020. I joined for the rebuild and replatform of its service-job apps and three new feature areas: unscheduled work, a digital double pole form, and self-boarding for new users.

What I owned

  • Product strategy and design for the rebuild and the three new feature areas
  • Process maps of crew, supervisor and back-office work, to find the steps OMW could automate
  • Business and data analysis linking the app to its parent systems
  • Prototypes built with engineering and SMEs, tested with users and approved in mid-sprint reviews
  • High-fidelity designs for desktop, tablet and mobile on the company design system, user-tested for ADA compliance
  • Product management for three months, as interim PM

What I don't claim

  • The 45% to 83% result alone. It belongs to the whole team.
  • OMW's totals since its 2020 launch. They show adoption of the platform, not my results.
  • Digital confirming work requests (CWRs). I mapped the flow; the team piloted it after my time on OMW.
  • A close-out time figure. We defined how to measure it, and I'm not publishing the number.

Decisions and trade-offs

Three principles, eight decisions.

Each decision had an option I turned down and something it cost.

01 · scope

Prove a small loop first

  1. Start with short-cycle jobs only

    WhyOverhead Service and Streetlight requests under six man-hours, in Massachusetts and New York, were the high-volume jobs where paper cost crews the most time.

    Turned downDigitizing every type of work in one release.

    Gave upCoverage. Underground, substation and larger project crews stayed on paper at launch.

  2. Let SMEs stand in for crews we couldn't reach

    WhyCrew time was limited. Subject-matter experts filled the gaps in the personas, tasks and hand-offs, so design could start.

    Turned downHolding the design until we had more time in the field.

    Gave upFirst-hand observation. SME assumptions stayed unproven until usability testing checked them with real users.

  3. Agree how to measure before launch

    WhyThe clock starts when a supervisor approves and stops when the last close-out requirement is marked complete. Agreeing those two timestamps up front made before and after comparable.

    Turned downWorking out the impact after launch, from whatever data existed.

    Gave upThe wider picture. That window measures close-out, not the drives and phone calls saved in the field.

02 · the field

Keep crews at the job site

  1. Let crews claim their own work

    WhyA crew that can pick up its next job in the app doesn't need to call in or drive back for it.

    Turned downKeeping every assignment with the supervisor.

    Gave upSome supervisor control over who takes what. Assign and reassign stayed on the supervisor dashboard as the check.

  2. Fill in the timesheet from claimed work

    WhyOMW connects to the timesheet system, so each claimed work request's line items are filled in for the crew.

    Turned downA faster form that crews still fill in by hand.

    Gave upIndependence. The feature only works while OMW stays in step with the timesheet system.

  3. Capture photos in line, not in a dialog

    WhyDialogs interrupted crews in the middle of a task. Removing them cut task time 32% in usability testing.

    Turned downThe first version, which opened a dialog over the job for photo capture.

    Gave upA deliberate stop at each photo. The photo is tagged to the job automatically instead.

03 · the back office

Take the paper out of the hand-offs

  1. Keep the supervisor's approval, automate what follows

    WhyOnce a supervisor approves, OMW files the paperwork and creates the record, so nobody re-keys it.

    Turned downA digital copy of the paper route, still passing from supervisor to clerk to work order completion.

    Gave upA second pair of eyes. The supervisor's approval became the one human check.

  2. Build jobs so they can move between crews and barns

    WhySupervisors need to assign and reassign a crew's work, especially during storms. The job structure was built with that in mind.

    Turned downA simpler model with each job fixed to one crew.

    Gave upBulk updates in the first release. Batch assign was still on the roadmap after my time on OMW.

Before and after

One screen: adding a site photo.

Crews attach site photos when they close out a job. The first version stopped them to do it. The second lets them keep going.

BeforeA dialog on top of the job. Adding a photo covered the close-out list. Crews had to deal with the dialog before they could get back to their place.
AfterCapture in line. Photos are added inside the close-out list and tagged to the job automatically. Nothing covers the work.

Simplified redraw with sample data, made for this page to show the change in interaction. Not production screens.

The same job, before and after OMW

BeforeWith OMW
Getting the next jobCall in, or drive back to the barnClaimed in the app, from the field
TimesheetEntered for each work requestFilled in from claimed work
Meter form and site photosPaper forms that could get lostCaptured on site
Paperwork to the supervisorHanded over on paperRouted in the app for approval
After approvalA clerk scans and forwards it, then it is keyed in againOMW files it and creates the record

What changed along the way

Three things that didn't work first.

Navigation

With the earlier navigation, 68% of tasks succeeded in testing.

Clearer navigation lifted task success to 95%.

Photo capture

Dialogs interrupted crews in the middle of the task.

Capture moved in line, and task time fell 32%.

Learning from crews

Learn the work from crews first-hand.

We got some time with crews, but not enough. SMEs covered what we couldn't observe, and usability testing checked their assumptions.

Impact

Crews chose the app over paper.

45% → 83%

Share of jobs crews completed in the app, instead of on paper or by calling in.

68% → 95%

Task success in usability testing, after the navigation rework.

32% less time

Task time in usability testing, after photo capture moved in line.

2 fewer hand-offs

Paper no longer passes from supervisor to clerk, or from clerk to work order completion.

No paper

Short-cycle jobs are delivered in the app in Massachusetts and New York.

Chairman's Award

National Grid recognized the project.

The first number is measured adoption. The second and third come from usability testing, not live use. I'm not publishing the close-out time figure.

What came next

The narrow start left a long list.

OMW kept growing after my time on it. The team's plan tied each quarter to an outcome, not a list of features.

Reflection

What I learned.

The biggest savings sat with people who never open the app.
FULL CASE STUDY
Process maps, the supervisor dashboard and the roadmap
Open →
BACK TO
All work
See all →

Public version of a National Grid project, shared as a portfolio piece. Screens are redrawn with sample data. This page holds no customer data, real addresses or internal screenshots.